Project Overview

Under construction district party office building for BJP in Mulugu, Telangana, featuring structural RCC frame columns, secure boundary walls, and modern spatial design.

Scope of Civil Works

  • Excavating and laying primary concrete foundations.
  • Erecting structural reinforced concrete columns.
  • Curing concrete structural elements to full load strength.
  • Constructing secure themed boundary walls.

Technical Challenges Faced

Sourcing high-quality water and aggregates in a remote district location to maintain concrete strength standards.

Engineering Solutions Deployed

Implemented on-site water filtration and strict aggregate testing to ensure structural concrete stability during column casting.

Field Operations PWA

Project Planning Workspace

Interactive field tracking for site supervisors, quality audits, and milestone completion verification (BJP District Office — Mulugu • Mulugu, Telangana).

Site Telemetry: Active

Construction Stage Pipeline

Field-friendly milestone tracking. Drag sliders to log verified completion percentages directly from site.

Glove-Friendly Touch
Stage 01
100%

Topographic contour survey, GHMC perimeter hoarding, rock mechanical trenching, and PCC mud mat.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 02
100%

Tata Tiscon Fe550D rebar fabrication, anti-termite chemical soil injection, and raft slab pour.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 03
75%

RCC columns shuttering, M30 ready-mix transit pour, PT slab tensioning, and 21-day pond curing.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 04
40%

Autoclaved AAC / Red brick partitions, dual coat external waterproof plastering with Dr. Fixit admixtures.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 05
20%

Concealed PVC electrical conduits (Sudhakar), CPVC plumbing lines (Ashirvad), and HVAC duct sleeves.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 06
0%

Vitrified tiles / epoxy floor laying, premium weather-coat paint, electrical fixtures, and client key handover.

0% Initiated 50% In Progress 100% Milestone Achieved