Institutional/Public Project Case Study

Piduguralla Railway Station

Location: Guntur Division, Andhra Pradesh | Completion: August 2024

Project Overview

Station redevelopment featuring a central dome for architectural identity, terracotta-toned cladding, tensile fabric canopies in the forecourt, and solar-powered sustainable elements under the Amrit Bharat Station Scheme.

Scope of Civil Works

  • Reconstructing the main station building facade with a central identification dome.
  • Installing weather-resistant terracotta cladding panels on the exterior walls.
  • Fabricating and deploying high-strength tensile fabric canopies in the forecourt areas.
  • Upgrading passenger facilities, ticketing counters, platforms, and public circulation pathways.
  • Installing solar-powered green elements and sustainable water harvesting systems.

Technical Challenges Faced

Managing structural upgrades and heavy canopy installations inside an active railway station without disrupting daily passenger traffic and train schedules.

Engineering Solutions Deployed

Scheduled major lifting operations and structural dome works during designated night blocks and off-peak passenger hours. Deployed high-strength precast elements to speed up on-site assembly.

Field Operations PWA

Project Planning Workspace

Interactive field tracking for site supervisors, quality audits, and milestone completion verification (Piduguralla Railway Station • Guntur Division, Andhra Pradesh).

Site Telemetry: Active

Construction Stage Pipeline

Field-friendly milestone tracking. Drag sliders to log verified completion percentages directly from site.

Glove-Friendly Touch
Stage 01
100%

Topographic contour survey, GHMC perimeter hoarding, rock mechanical trenching, and PCC mud mat.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 02
100%

Tata Tiscon Fe550D rebar fabrication, anti-termite chemical soil injection, and raft slab pour.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 03
75%

RCC columns shuttering, M30 ready-mix transit pour, PT slab tensioning, and 21-day pond curing.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 04
40%

Autoclaved AAC / Red brick partitions, dual coat external waterproof plastering with Dr. Fixit admixtures.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 05
20%

Concealed PVC electrical conduits (Sudhakar), CPVC plumbing lines (Ashirvad), and HVAC duct sleeves.

0% Initiated 50% In Progress 100% Milestone Achieved
Stage 06
0%

Vitrified tiles / epoxy floor laying, premium weather-coat paint, electrical fixtures, and client key handover.

0% Initiated 50% In Progress 100% Milestone Achieved